Question: Project execution must be compared, and deviations must be measured for management control according to the a. Scope baseline b. Performance measurement baseline c. Schedule
Project execution must be compared, and deviations must be measured for management control according to the—
a. Scope baseline
b. Performance measurement baseline
c. Schedule baseline
d. Control system