Question: Projects are often started as a result of an external factor such as market demand for a new product, a new legislative or regulatory mandate,


Projects are often started as a result of an external factor such as market demand for a new product, a new legislative or regulatory mandate, or a change in technology. This results in the creation of ______ by an entity or organization external to the project.

A. the project charter B. the WBS C. the project budget.

D. the RACI chart