Question: Requirements for formal contract acceptance and closure usually are defined in the a. Proposal b. Statement of work c. Contract terms and conditions d. Procurement

Requirements for formal contract acceptance and closure usually are defined in the—

a. Proposal

b. Statement of work

c. Contract terms and conditions

d. Procurement audit report