Question: Since projects involve change, change requests then will be needed. Every documented change request must be approved by a responsible person, who is a. The
Since projects involve change, change requests then will be needed. Every documented change request must be approved by a responsible person, who is—
a. The project manager or the sponsor
b. A member of the CCB
c. Identified in the change management plan
d. Identified in the project management plan