Question: Stakeholder engagement must be controlled on a continuous basis for it to be effective. You realize a number of project documents can be useful for
Stakeholder engagement must be controlled on a continuous basis for it to be effective. You realize a number of project documents can be useful for you as a project manager. An example is—
a. Technical performance measures
b. Change log
c. Actual costs
d. Start and finish dates of schedule activities