Question: The ability for project stakeholders to influence the project scope and cost of a project is greatest during which phase of a project? A. Initiating
The ability for project stakeholders to influence the project scope and cost of a project is greatest during which phase of a project? A. Initiating B. Planning C. Executing D. Controlling 22. The cost of changes to project scope generally ______ over the life cycle of a project. A. Increase B. Decrease C. Stabilize D. None of the above