Question: The client asks you for some minor changes to the project and you discuss this matter with your team members. One of your team members

The client asks you for some minor changes to the project and you discuss this matter with your team members. One of your team members told you that he thinks that it will not affect any other project objective. What will you do now?

(a) Review the request according to integrated change control process

(b) Since the team member thinks it will not affect any project objective, implement it

(c) Ignore it

(d) None of the above