Question: The client has given you a project to install a new kind of elevator, so you start designing it from scratch. The planning phase is
The client has given you a project to install a new kind of elevator, so you start designing it from scratch. The planning phase is completed and you are now about to install the elevator. Suddenly a team member comes to you and asks for a change in the quality management plan as he has identified a flaw in the process. In which process can you perform the integrated change control?
(a) During the monitoring & controlling phase
(b) During the execution phase
(c) Throughout the project
(d) During the executing, and monitoring & controlling phase Go to the Answer