Question: The client has requested a change in a deliverable which you have processed through a change request and it is approved. Now, you are in
The client has requested a change in a deliverable which you have processed through a change request and it is approved. Now, you are in the process of implementing this change into the project. In which of the following processes do you implement the approved change?
(a) Monitor and control project work
(b) Direct and manage project work
(c) Perform integrated change control
(d) Control scope