Question: The client is asking for many changes in the project which is causing you to change the baseline many times. You are constantly estimating the
The client is asking for many changes in the project which is causing you to change the baseline many times. You are constantly estimating the cost of impact and raising the change request, and once it is approved, you will update the cost baseline. Which of the following should be updated frequently?
(a) Cost baseline
(b) Schedule baseline
(c) Lessons learned
(d) Project charter Go to the Answer