Question: The earned value on your project is $26,000, the planned value is $20,000, and the actual cost is $18,000. What is your schedule variance? A:

The earned value on your project is $26,000, the planned value is

$20,000, and the actual cost is $18,000. What is your schedule variance?

A: $6,000 B: $8,000 C: -$8,000 D: $2,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!