Question: The earned value on your project is $26,000, the planned value is $20,000, and the actual cost is $18,000. What is your schedule variance? A:
The earned value on your project is $26,000, the planned value is
$20,000, and the actual cost is $18,000. What is your schedule variance?
A: $6,000 B: $8,000 C: -$8,000 D: $2,000
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
