Question: The key inputs to the validate scope process include all the below items EXCEPT a. The project management plan (scope management plan and scope baseline)

The key inputs to the validate scope process include all the below items EXCEPT—

a. The project management plan (scope management plan and scope baseline)

b. Change requests

c. Validated deliverables

d. Requirements traceability matrix