Question: The linkages between Project Management Process Groups are best described by the following: A. The Work Breakdown Structure links Process Groups. B. Process Groups are
The linkages between Project Management Process Groups are best described by the following: A. The Work Breakdown Structure links Process Groups. B. Process Groups are linked by their planned objectives-the summary objective of one often becomes the detailed action plan for another. C. Process Groups are linked by the objectives they produce the output of one process often becomes an input to another process, or is a deliverable of the project. D. There are no significant links between discrete Process Groups.