Question: The primary advantage of using decision-tree analysis in project risk management is that it a. Considers the attitude of the decision maker toward risk b.

The primary advantage of using decision-tree analysis in project risk management is that it—

a. Considers the attitude of the decision maker toward risk

b. Forces consideration of the probability of each outcome

c. Helps to identify and postulate risk scenarios for the project

d. Shows how risks can occur in combination