Question: The primary output of the close project or phase process is A. Formalize and distribute all information pertaining to the project closing B.
The primary output of the close project or phase process is ❍ A. Formalize and distribute all information pertaining to the project closing ❍ B. Lessons learned ❍ C. Release all personnel assigned to the project ❍ D. Get customer and sponsor approval ❍ E. B and D