Question: The project baseline: A. Encompass all the initial estimates for tasks and resource utilization B. Is only important in the project initiation phase C. Is

The project baseline: A. Encompass all the initial estimates for tasks and resource utilization B. Is only important in the project initiation phase C. Is the result of the original plans plus the approved changes D. Is not needed to successfully manage a project