Question: The project team has created a plan for how they will implement the quality policy. It addresses the organizational structure, responsibilities, procedures, and other information
The project team has created a plan for how they will implement the quality policy. It addresses the organizational structure, responsibilities, procedures, and other information about plans for quality. If this plan changes during the project, WHICH of the following plans will also change? A. Quality assurance plan B. Quality management plan C. Project management plan D. Quality control plan