Question: There are two activities on your schedule, which are: 1) Install server in lab 2) Move server into the data center. However, the second task
There are two activities on your schedule, which are: 1) Install server in lab 2) Move server into the data center. However, the second task can't start until the server has run in the lab for 5 days without failure. This is an example of what?
A. Fast Track B. Lead C. Crashing D. Lag