Question: To practice effective schedule control, your project team must be alert to any issues that may cause problems in the future. To best accomplish effective
To practice effective schedule control, your project team must be alert to any issues that may cause problems in the future. To best accomplish effective schedule control, the team should—
a. Review work performance information
b. Allow no changes to the schedule
c. Update the schedule management plan on a continuous basis
d. Hold status reviews