Question: What should be the primary driving factor in choosing a method for project management? A. It should have a proven track record of success B.

What should be the primary driving factor in choosing a method for project management?

A. It should have a proven track record of success B. It should be the easiest method available C. It should be capable of achieving the desired outcome, result, or deliverable D. It should be the most recent method developed