Question: Which is an acceptable cause for re- baselining a $10 million project? A. The client has authorized a $100,000 addition to the scope of the
Which is an acceptable cause for "re- baselining" a $10 million project? A. The client has authorized a $100,000 addition to the scope of the project. B. The contractor's company has instituted a Quality Program in which it has pledged to spend one million dollars during the next year. C. The productivity in the Drafting Department is lower than anticipated, which has resulted in 1,000 additional hours over what was budgeted. D. The Engineering Department has converted to a new $200,000 CAD system.