Question: Which is an acceptable cause for re- baselining a $10 million project? A. The client has authorized a $100,000 addition to the scope of the

Which is an acceptable cause for "re- baselining" a $10 million project? A. The client has authorized a $100,000 addition to the scope of the project. B. The contractor's company has instituted a Quality Program in which it has pledged to spend one million dollars during the next year. C. The productivity in the Drafting Department is lower than anticipated, which has resulted in 1,000 additional hours over what was budgeted. D. The Engineering Department has converted to a new $200,000 CAD system.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!