Question: Which of the following process groups involves people and resources coordination, stakeholder management, as well as integrating and performing the activities of the project in


Which of the following process groups involves people and resources coordination, stakeholder management, as well as integrating and performing the activities of the project in accordance with the project management plan?

A. Executing Process Group B. Monitoring & Controlling Process Group C. Initiating Process Group D. Planning Process Group