Question: Which process in the Project Integration Management knowledge area deals with making decisions on change requests? A. Monitor and Control Project Work B. Develop Project
Which process in the Project Integration Management knowledge area deals with making decisions on change requests?
A. Monitor and Control Project Work B. Develop Project Charter C. Direct and Manage Project Work D. Perform Integrated Change Control