Question: While completing your risk management plan you also decide to create a fallback plan. What is the main reason for creating a fallback plan? A:

While completing your risk management plan you also decide to create a fallback plan. What is the main reason for creating a fallback plan?

A: To deal with known risks with a large uncertainty about the probability of occurrence.

B: Unknown risks that cannot be managed proactively.

C: Unknown risks that have been identified in the risk management plan.

D: Known risks that if they occur can have a larger-thananticipated impact on your project.