Question: While finalizing the WBS you assign each work package to a control account and establish a unique identifier for the same work from a code
While finalizing the WBS you assign each work package to a control account and establish a unique identifier for the same work from a code of account. These identifiers help you find a hierarchical sum of costs, schedule, etc. Which statement is true about the WBS?
(a) It contains all project work
(b) It authorizes the project manager
(c) It is a hierarchy of project staff
(d) It is a hierarchical breakdown of project resources
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts