Question: While in the executing phase of a project, a functional manager informs you that he will not have sufficient resources available next month to support
While in the executing phase of a project, a functional manager informs you that he will not have sufficient resources available next month to support your project and two other projects. How should you handle this situation? ❍ A. Ask the functional manager to make the decision ❍ B. Ask the functional manager to work with his management to prioritize the work ❍ C. Ask your sponsor to meet with the functional manager ❍ D. Ask the functional manager to set up a meeting with you and the other project managers to work out the problem yourselves