Question: While you have worked as a project manager for ten years, you are new to your current organization. In the past, your organization was informal

While you have worked as a project manager for ten years, you are new to your current organization. In the past, your organization was informal in terms of plans to prepare and processes to follow. Your new organization, however, requires that each project have a human resource management plan. You are unsure of the reporting relationships that need to be followed. You decide to—

a. Hold meetings with the team members who have been assigned thus far

b. Use experts

c. Develop a RACI chart and review it with your sponsor

d. Use your WBS and develop a hierarchical organization chart

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!