Question: While you have worked as a project manager for ten years, you are new to your current organization. In the past, your organization was informal
While you have worked as a project manager for ten years, you are new to your current organization. In the past, your organization was informal in terms of plans to prepare and processes to follow. Your new organization, however, requires that each project have a human resource management plan. You are unsure of the reporting relationships that need to be followed. You decide to—
a. Hold meetings with the team members who have been assigned thus far
b. Use experts
c. Develop a RACI chart and review it with your sponsor
d. Use your WBS and develop a hierarchical organization chart