Question: Work performance data often are used In Control Procurements to show a. Whether quality standards are being satisfied b. If approved change requests are being

Work performance data often are used In Control Procurements to show—

a. Whether quality standards are being satisfied

b. If approved change requests are being implemented

c. Current or potential problems

d. Compliance with contracts