Question: You and your project team are systematically gathering and analyzing quantitative and qualitative information to determine which stakeholders interests should be taken into account throughout

You and your project team are systematically gathering and analyzing quantitative and qualitative information to determine which stakeholder’s interests should be taken into account throughout the project. You have identified the interests, expectations, and influence of individual stakeholders and related to them the purpose of the project. What tool or technique are you using?

A: Meetings B: Expert judgment C: Information gathering techniques D: Stakeholder analysis