Question: You are assigned to prepare the Procurement Management Plan for a project that involves setting up an org-wide supply chain management system. You are looking
You are assigned to prepare the Procurement Management Plan for a project that involves setting up an org-wide supply chain management system. You are looking for a guideline on what type of contracts you can use and what type of contract forms are to be used for this project. Which source will help you obtain this?
A. Each project is unique so you will need to prepare the necessary documentation for this.
B. Department process repository C. Organizational Process Assets D. Integrated project Plan