Question: You are in a process which helps you evaluate the effectiveness of the risk process throughout the project. Which of the following documents will not
You are in a process which helps you evaluate the effectiveness of the risk process throughout the project. Which of the following documents will not be updated here?
(a) Assumption log
(b) Issue log
(c) Risk report
(d) Change log