Question: You are the project manager on a large project to develop a new customer information database for your organization. You are currently assessing the merits

You are the project manager on a large project to develop a new customer information database for your organization. You are currently assessing the merits of developing key components of the required software in-house by your own development team compared to getting an external contractor to complete the work.

What technique are you using?

A: Risk-related contract decisions B: Make-or-buy analysis C: Source selection criteria D: Expert judgment