Question: You are using a matrix-based chart to give a clear indication of the connection between work packages and team members. Additionally, the chart shows who
You are using a matrix-based chart to give a clear indication of the connection between work packages and team members. Additionally, the chart shows who is responsible, accountable, consulted, and informed about the work. What is the common name of this type of chart?
A: RACI chart B: Organizational breakdown structure C: Work breakdown structure D: Responsibility assignment matrix