Question: You are working on a project where a negative risk has occurred. However, you have no contingency plan for this risk. You call a meeting


You are working on a project where a negative risk has occurred. However, you have no contingency plan for this risk. You call a meeting and a solution is devised to change the workflow until a permanent solution can be implemented. This is an example of?

A. Work Item B. Workaround C. Work Package D. Reserve plan