Question: You are working on a project which is under budget and ahead of schedule. The project is 85% complete, and the client comes and asks
You are working on a project which is under budget and ahead of schedule. The project is 85% complete, and the client comes and asks you to terminate the project because he fears a possible regulation can impact his project. You review the project parameters and find that you can complete the project before the proposed legislation comes into existence; moreover, you won’t need any extra funding. What will your next steps be?
(a) Tell the client about your findings and ask him to reconsider his decision
(b) Initiate the close project process
(c) Immediately release your team members
(d) Convince your management to discuss the issue with the client