Question: You have been given a project to construct a small dam. Currently, you are visiting your project stakeholders and asking about their needs and expectations.

You have been given a project to construct a small dam. Currently, you are visiting your project stakeholders and asking about their needs and expectations. You also have had many workshops and brainstorming sessions with them. Which process is this?

(a) Identify stakeholders

(b) Collect requirements

(c) Define scope

(d) Control scope