Question: You have completed the final steps to develop a complete risk register with identified risks, a priority assessment, a qualitative assessment of all risks, a
You have completed the final steps to develop a complete risk register with identified risks, a priority assessment, a qualitative assessment of all risks, a quantitative assessment of the top priority risks, and you have also identified appropriate risk responses for each risk. Which of the following is not an expected output from completing this work?
A: Project document updates B: Project management plan updates C: Updates to the cost management plan D: Contingent response strategies