Question: You have completed your estimates for your project and determined that it will take 10 months to complete. However, your project sponsor insists that it
You have completed your estimates for your project and determined that it will take 10 months to complete. However, your project sponsor insists that it be completed in 9 months. How do you handle this?
A. Increase the budget by 10%
B. Inform the sponsor you will have to explore the options before committing to that timeline.
C. Reduce scope D. Add resources