Question: You have decided to apply Resource Leveling to a project due to a critical required resource being available only at certain times. Which of the


You have decided to apply Resource Leveling to a project due to a critical required resource being available only at certain times. Which of the following will likely be true?

A. Resource Leveling can often cause the original critical path to change.

B. Resource Leveling will over allocate resources to schedule the project before the deadline.

C. Resource Leveling will require additional resources to complete the project.

D. Resource Leveling will never alter the original critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!