Question: You have decided to study for the PMP credential and are currently learning the way in which the project life cycle can be described
You have decided to study for the PMP ® credential and are currently learning the way in which the project life cycle can be described in terms of process groups associated with initiating, planning, executing, monitoring and controlling, and closing activities. You then move on to studying the ways in which successful communication occurs in a project. In order to demonstrate how much you have learned, you are able to describe to a colleague how some aspect of project communication occurs in different process groups. The Manage Communications process occurs within which PMBOK ® Guide process group?
A: Initiating B: Planning C: Executing D: Monitoring and Controlling