Question: You have recently started working as a project manager for a health insurance portal development project. The project sponsor tells you that due to the
You have recently started working as a project manager for a health insurance portal development project. The project sponsor tells you that due to the critical nature of the project the work must start immediately and complete in two weeks. Based on the instructions, you have started documenting major constraints and assumptions to perform the project feasibility study. What should you do if you are able to prepare only the high-level feasibility study in the given time frame?
A. Conduct the stakeholder meeting to evaluate other options B. Escalate this issue to the sponsor and explain the need for more detailed study C. Submit the high level study and start making plans to prepare the charter D. Submit the high level study and schedule a detailed study in the planning phase