Question: Your budget at completion is $50,000, your earned value is $40,000, and your actual cost is $45,000. Using an estimate at completion forecast for ETC

Your budget at completion is $50,000, your earned value is $40,000, and your actual cost is $45,000. Using an estimate at completion forecast for ETC work performed at the present CPI, what is your estimate at completion?

A: $47,666 B: $50,000 C: $56,818 D: $53,225