Question: Your project is 60% complete and while reviewing the lessons learned document you notice that it has missed a few lessons you have learned recently.
Your project is 60% complete and while reviewing the lessons learned document you notice that it has missed a few lessons you have learned recently. You call all your team members and tell them to update the lessons learned as they happen. On any project, who is responsible for updating the lessons learned?
(a) Project manager
(b) Project management team
(c) Quality control personnel
(d) Quality assurance personnel Go to the Answer