Question: Your project management plan has been approved, and since your company follows a stage-gate approach, you are now in the executing phase. You have collected
Your project management plan has been approved, and since your company follows a stage-gate approach, you are now in the executing phase. You have collected a lot of data, and these data are viewed as—
a. Ones set forth in the PMIS
b. The lowest level of detail to derive information
c. Ones recommended through a survey of your stakeholders to assess their key communications requirements
d. A major part of the project management plan