Question: Your team is using your risk register to prioritize risks for further analysis by assessing their probability of occurrence and impact. What PMBOK Guide
Your team is using your risk register to prioritize risks for further analysis by assessing their probability of occurrence and impact. What PMBOK ® Guide process best describes the work they are carrying out?
A: Plan Risk Management B: Perform Quantitative Risk Analysis C: Identify Risks D: Perform Qualitative Risk Analysis