Question: Hoosier Power needs to determine a capacity expansion plan to meet Bloomingtons power needs for the next 20 years. The current capacity is 5000 kwh.
Hoosier Power needs to determine a capacity expansion plan to meet Bloomington’s power needs for the next 20 years. The current capacity is 5000 kwh. The demand for the current year is 4000 kwh, and demand is expected to increase by 1000 kwh in each succeeding year. At the beginning of each year, Hoosier Power must determine the amount of capacity to add, given the following inputs:
■ Any year in which capacity is added, a fixed cost of $120,000 is incurred plus a cost of $120 per kwh of capacity.
■ At most 10,000 kwh of capacity can be added in a single year.
■ It costs $25 per year to maintain a unit of capacity.
■ It costs $12 per year to produce a kwh.
■ If production does not meet demand, a shortage cost of $80 per kwh short is incurred. Develop a linear integer model to help Hoosier Power minimize its costs for the next 20 years.
Step by Step Solution
3.31 Rating (160 Votes )
There are 3 Steps involved in it
Power company capacity expansion Fixed cost for capacity 120000 Unit capacity cost 120 Unit maintena... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (3 attachments)
1497_60b741247a9cd_696548.pdf
180 KBs PDF File
1497_604601381b36f_696548.xlsx
300 KBs Excel File
1497_60b741247a9cd_696548.docx
120 KBs Word File