Question: Same as before, except that the project has the option to contract. The static project value now is $146 million, the standard deviation of static

Same as before, except that the project has the option to contract. The static project value now is $146 million, the standard deviation of static project value is 63.0%, the riskfree rate is 0.00%, the project can be contracted by 55%

at any time for contraction savings of $75.0 million, the time to project completion is 2.4 years, and an 8 period binomial model will be used. When should the project be contracted? What is the flexible project value? What is the value of the option to contract?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Principles Corporate Finance Questions!