Question: Roger is developing a risk register for his first risk workshop. During the workshop he and some SMEs are going to classify some risks. Which
Roger is developing a risk register for his first risk workshop. During the workshop he and some SMEs are going to classify some risks. Which of the following would be the best classification?
A. Positive and negative threats B. Threats or opportunities C. Risks and issues D. Probability and impact