Question: Consider the network scheduling problem as shown below. Duration Manpower Activity (Months) Required 1-2 5 12 1-3 6 4 2-3 8 6 2-4 7 3
Consider the network scheduling problem as shown below.
Duration Manpower Activity (Months) Required 1-2 5 12 1-3 6 4 2-3 8 6 2-4 7 3 3-4 4 8 Schedule the activities of the project with a maximum limit on the manpower requirement as 12.