Question: E.24 If the first unit of a production run takes 1 hour and the firm is on an 80% learning curve, how long will unit
• • E.24 If the first unit of a production run takes 1 hour and the firm is on an 80% learning curve, how long will unit 100 take?
(Hint: Apply the coefficient in Table E.3 twice.)